The biggest claim to the organizer of the Olympic Games in "Gazprom" (1.29 billion rubles.) And a subsidiary of RZD structure (4.42 billion rubles.). However, if "Olimpstroy" does not find means nothing will recover.
«Olympstroy» was established for the preparation and holding of the Olympic and Paralympic Winter Games in Sochi in 2014 and acts as the customer of construction of Olympic facilities from the federal budget. "Olympstroy" became the customer of large ice arena (9,9 bln.), The central stadium "Fischt" (17.5 billion), the Little Ice Arena (1 bln.), Bobsleigh track (2.5 billion rubles .), the palace for figure skating (8,8 bln.). Just as a contribution to the charter capital of "Olimpstroya" from the budget of 211.6 billion rubles was allocated for 2008-2014. According to the Regional Development Ministry estimated the total cost of training for the Olympics amounted to 1.5 trillion rubles.
Under federal law, the summer elimination procedure was introduced in the company. Chairman liquidation committee became the first vice-president of "Olimpstroya" Hamit Mavliyarov. It was his team, according to the decision of the Government mustwill collect funds from debtors and meet creditors' claims, and the remaining money to pass the budget. In addition, "Olimpstroy" will have to pass several billion rubles unused subsidies in the federal budget.
Claims mutual
To date, according to the site of the Arbitration Court considered 14 cases of former contractors "Olimpstroya" to its customers. The total amount of claims of 5.8 billion rubles. The largest claim filed subsidiary of "Russian railways" "RZDstroy", it claims amount to 4.42 billion rubles. The Olympic Games in 2014 Russian Railways had to build in Sochi and its environs six sites. Among them, a combined road and railway between Adler and the mountain climatic resort "Alpika-Service", the railway line from Adler station to the airport, railroad freight yards in the Imereti lowland, dormitory (49 rooms), in the sanatorium "Cape of Prominent". Later, however, the company has started the construction of Olympic infrastructure. The Railways and "RZDstroy" the fate of the claim is not commenting.
Two of the claim in the total amount of 1.8 billion rubles. He filed "Gazprom". In such a figure he estimated penalty. The third party in this litigation acts "Sotsinvest Gazprom", which implemented projects for construction of ski and biathlon complex Psekhako Ridge, mountain Olympic village for skiers and biathletes. "Gazprom" is also built for the Olympic Games and the Adler CHPS gas pipeline Dzhubga - Lazarevskoye - Sochi. In "Gazprom" RBC request left unanswered. A source close to the company said that "Olimpstroy" also filed counterclaims, the amount of which is higher.
Get comments "Olimpstroj" RBC failed: phone reception "Olimpstroya" is turned off, phone calls no one answered the Legal Department.
As the senior lawyer Herbert Smith Freehill Roman Churakov, counterparties' Olimpstroya "could forego what is due them under contracts with the corporation, as it is written in the law. "Another law came into force, under which started liquidation" Olimpstroya "in July 2014. According to it, the requirements of counterparties to State Committeerporatsii may be claimed only until 14 October. But even in the case of application requirements in this term lenders must keep in mind that the law forbade them to collect from the corporation money and other valuables stored in banks, as well as the demand for repayment of debt the sale of any Olympic property, constructed by "Olimpstroya" - said the lawyer. According to him, the lenders also have no right to demand anything from the Russian Federation or the federal budget. In fact, for the payment of debts to contractors can only other (non-Olympic) property owned by the corporation. "In any case, we believe that these rather stringent conditions were expected liquidation of the corporation, and counterparties were to be ready for them," - said Roman Churakov.
Olympics bankrupt builders
"Tunnel Brigade №44»
February 12 procedure observation of "Tunnel Brigade №44» (Sochi) was introduced. The lawsuit in bankruptcy filed a Federal State Unitary Enterprise "Bridges and tunnels". The total amount of the claims of creditors - about 5 billion rubles. Among the Baovert Olympic projects of the company - the first stage doubler Resort prospectus.
NGO "Mostovik"
June 26, the court entered against the NGO "Mostovik" monitoring procedure. claims Gazprombank, Alfa-Bank is now in the Moscow Arbitration Court considered and LLC "KIT Finance Capital" to recover from the "bridge-builders" of more than 7 billion rubles. The company was the general contractor of reconstruction of sewers in Sochi, reconstruction of sewage pumping stations "Kudepsta" and "Semashko", and also engaged in the construction of utilities to the land borders of the Olympic facilities.
"Kubandorblagoustroystvo"
July 4 Arbitration Court of Krasnodar region has introduced a procedure for monitoring of "KDB" (Krasnodar). The main Olympic facilities of the company are construction of a highway in the Imereti lowland, and transport interchanges "Adler Ring".
"Tonneldorstroy"
October 17th Arbitration Court of Krasnodar region declared LLC "Tonneldorstroy" (Krasnodar region)ankrotom and opened against the company's bankruptcy proceedings for a period of six months. "Tonneldorstroy" in 2010-2012 has been declared the winner of 15 open requests for proposals for the construction and reconstruction of sections of roads and road junctions in the territory of Sochi on the total amount of 9.46 billion rubles.
After the ball
Some contractors "Olimpstroya" money is no longer needed. At the moment, the courts decisions of the bankruptcy or enforcement proceedings in five construction companies. Earlier, they performed a multibillion-dollar contract for the construction of Olympic facilities. The last thing was the recognition of October 17 bankruptcy LLC "Tonneldorstroy" (Krasnodar region), which has built several roads for the Olympic Games and the complex of springboards. But the biggest and loud was the introduction of the Arbitration Court of Omsk Region procedure observation for four months. Omsk "NPO" Mostovik "engaged in the design and construction of Olympic facilities in Sochi - Grand Ice Arena for ice hockey for 12 thousand places, bobsleigh track and Ob.transport infrastructure projects.