Starting the project "RusHydro" in the Far East once again transferred, he said in an interview to "Interfax" the general director Nikolai Shulginov company. "In 2018 in the Far East are planned launches the first phase of the Sakhalin GRES-2 and TPP in the city Sovetskaya Gavan capacity of 120 MW each," - said a top manager.
The decision forced and associated with defaults on the part of contractors, explains the representative of "RusHydro". On Sakhalin GRES-2 general contractor "TEK Mosenergo" was forced to change the subcontractor, he explains, is now eliminated violations and work is being done in an intensive mode. On CHP in Sovetskaya Gavan delay is due to lack of funds from the contractor - "GlobalElektroServis". Co by "RusHydro" financing was carried out in a timely manner, he emphasized the spokesman.
In the Far East, "RusHydro" build four large power: CHP in Sovetskaya Gavan, primarily the Sakhalin GRES-2, primarily the Yakutsk GRES-2 and the second stage of the Annunciation CHP. Work carried out in 2012 to 50 billion rubles were allocated for these purposes from the budget. CHP in Sovetskaya Gavan, and all have the Sakhalin GRES-2 have been delivered in 2016, and the CHP units at the Annunciation and at the Yakutsk GRES-2 - in 2015. Power plants need to upgrade the power grid and improve reliability to meet the demand of industrial consumers .
Shulgin, who succeeded in September 2015, the post of general director of "RusHydro" Yevgeny Dod, in the first days after his appointment in a letter to President Vladimir Putin reported on with the construction of a problem - for example, the basic equipment has been selected. As a result, new terms have been agreed for the three stations - Yakutsk GRES-2 (2016), the Sakhalin GRES-2 and CHP in Sovetskaya Gavan (both - 2017). Additional Agreement to the Federal Property Management Agency and the Department of Energy suggests the penalty for missed deadlines - 5% of the funds allocated by the state. In early December, the right to dispose of shares in the four Far East stations were transferred to "RusHydro" from her "daughter" of "RAO ES of the East". The parent company has decided to complete the construction by yourself.
The report "RusHydro" for the first nine months of the IFRS states that the company has returned to the budget balance is not used for the construction of funds in the amount of 7 billion rubles. A total of Sakhalin GRES-2 left to spend 24.2 billion rubles. (The construction was estimated at 34.8 billion rubles.), On the CHP in Sovetskaya Gavan - 7.9 billion rubles. (Total cost -. 18.6 billion rubles), follows from the report.
"RusHydro"
The energy
The main shareholder - the Federal Property Management Agency (66.84%).
Capitalization - 345 billion rubles.
Revenue (IFRS 9 months 2016) - 268.6 billion rubles.
The net profit - 37.4 billion rubles.
The idea was the replacement of the old power, over time it did not younger, so the need for updating it still persists, Raiffeisenbank analyst Fyodor Kornach.
The other day, "RusHydro" has launched the first of four facilities - the second stage of the Annunciation CHP. But the launch of the Yakutsk GRES-2 will still be postponed to 2017 due to the increase in the cost of work, according to "RusHydro".
The tariff for new power Annunciation CHP was 40% higher than that of the old, it resembles the head of group research and forecasting ACRA Natalia Porokhova. But in non-price zone of the Far East and has a station with higher tariffs for power, she said. The average level of deterioration of the generating equipment "RAO ES of the East" is 78%, emphasized in an interview Shulginov. Branches need drastic tariff decision, to provide a return on investment in modernization, he said: "There are objects in which investment will not pay off ever."